[BLAST_SHIFTS] Shift summary 04/11/2004 E (16-20)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Sun Apr 11 2004 - 20:05:56 EDT


Operators: ajmasch akdogan clasie

Taylan downloaded the trigger before he left at 16:00. After this, we took data until 19:30 when there was a power glitch. CCR said it was going to be a while until we get beam back. Valves 10 & 11 on the ABS closed and the plasma turned off. We called Genya, and he said to turn the off the flow and RF. Chris Vidal will be coming in to restart the ABS.