[BLAST_SHIFTS] Shift summary 02/27/2005 B (9-17)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Sun Feb 27 2005 - 17:17:20 EST


Operator: nikolas

one good run.
problems with the wire chambers, L21 tripping, see elog.
miraculously stopped when aaron ramped up the fields on the wires slowly.
Micheal demanded beam tuning with BLAST field off around 2pm. CCR tuning since.



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:32 EST