   ABS data taking until midnight. Frequent HV trips forced to lower HV on R5 from 3850 to 3830.
   Also, beam life time problem still remains, so fill were done only to 135 mA.
   Switched to empty target at 12:40.
   Unpol system is filled with Hydrogen and ready to g0.