[BLAST_SHIFTS] Shift summary 09/17/2003 F (20-24)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Thu Sep 18 2003 - 00:14:54 EDT


Operators: hasell ---- ----

Hall open in the afternoon to fill snakes. We will not open Thursday unless something unforeseen happens.

Hall closed around19:00 and beam restored around 20:00.

Re-established tune for an empty target, reversed toroidal field, and no holding field.

While the hall was open fixed a couple of missing channels in the wire chambers but there are still a couple missing and two hot channels.

Started collecting data. Runs 2638 - 2642.

HV crate hung once and needed to be power cycled and have the IOC rebooted. This probably caused CODA and Compton to hang.

WC L21 tripped twice.

Otherwise very smooth running.
Started running



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:30 EST