Snakes were partially filled today. Will probably need to be re-filled
Monday or Tuesday.

LADS detectors were moved down to the South Hall floor. Plan will be
to install them Monday and Tuesday.

ABS will be removed Monday

Longitudinal holding field was reversed.

Plan for tonight is to measure the atomic fraction and then resume
normal data taking but with the holding field reversed.

                                                                         