[BLAST_SHIFTS] Shift summary 08/26/2003 B (4-8)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Tue Aug 26 2003 - 06:18:39 EDT


Operators: karpiusp chris2 ----

Beam tuning through beginning of shift.
CCR made a -2mm hz bump achieving a lifetime of 37 min @ 90 mA
BQM U was 350 w/ slits out

I asked that the BQMs be checked and optimized with slits in.
BQM U was lowered to about 211. Took empty target run 2134 and plotted zwl and zwr, see (elog) below image.

Bill Franklin called and asked if he could start compton work, I told him that was fine.

CCR continued to tune during crunching of run 2134

                                                PK