[BLAST_SHIFTS] Plan for this week.

From: Douglas Hasell (hasell@MIT.EDU)
Date: Mon Jan 13 2003 - 11:28:14 EST


To organise the day to day work which needs to be done during the shutdown
there will be organisational meetings every Monday and Wednesday.

Following today's meeting the plan is:

        - work will proceed on the ABS
        - plan to turn on the BLAST Toroid for ABS studies ~Thursday+/-1day
        - work should proceed on the TOF and Cerenkov to replace bad tubes
        - the magnetic field test on the empty Cerenkov tube should be
prepared in time for ~Thursday when the toroid will be powered for ABS
        - the maintenance work on the BLAST frame, cables, gas lines should
start
        - the nitrogen flush of the wire chamber entrance / exit windows
should be installed
        - bad wire chamber boxes should be replaced

        There will be a general shutdown meeting to coordinate the work and
manpower for the shut down Wednesday at 15:00.

                                                  Cheers,
                                                          Douglas

26-415 M.I.T. Tel: +1 617 258 7199
77 Massachusetts Avenue Fax: +1 617 258 5440
Cambridge, MA 02139, USA E-mail: hasell@mit.edu



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:29 EST