At this morning's BLAST coordination/commissioning meeting, the
following schedule has (tentatively) been agreed upon:
8/14 - 8/16 hall will be open during days for ABS work and WC
noise work; Compton polarimeter will run at night
8/17 - 8/18 weekend will be devoted to a combination of ABS
measurements and 3 shifts of data on ep with B ON;
Compton continues at night
8/19 - 8/20 wire target to be installed (contingent on solution
of WC noise problem); ABS measurements continue
8/21 - 8/28 WC data on wire target with B=0 (again contingent
on solution of noise problem); GRC tour on 8/23 AM;
DOE site visit 8/26
8/29 - 9/06 major installation of neutron bars, ABS (allowing
for above contingencies); Labor Day 9/2